December 2015

.December 2015

December 2015

.December 2015

September 2015

.September 2015

July 2015

.July 2015

June 2015

.June 2015

May 2015

.may 2015

April 2015

The construction is still going when the severe storm strikes Sydney, main services connections start in basement.

.

March 2015

Concrete work has been finished for ground level construction.

.

Mid-Feb 2015

Trans-slab is finished, construction is heading for super-structure.

.

Early-Feb 2015

Construction for level 1 basement has been started.

.

January 2015

Concrete work carry on for the second level basement.

.

December 2014

Level 2 basement is under construction.

.

November 2014

Site cleaning finished, and preparing for structure construction.

.

October 2014

Work while raining, in order to clean the site for basement construction.

.

September 2014

Piling finished, following with capping beams.

.

Late August 2014

Piling finished, after carefully examined by our engineers, the project reached another stage for excavation.

pic5

Early August 2014

Piling continues, to speed up the process, the company supervised the work putted two machines working at the time.

pic4

Late July 2014

Piling started from western boundary, even though the weather is raining for weeks.

pic3

June 2014

All demolition and preliminary ground works has been finished, the site is prepared for Piling.

pic2

May 2014

Demolition for Existing building has started from May 2014 and finished within this month, ground pavement has been removed for future works.

pic1